Monday, February 8, 2010
February 8, 2010 Update
Also, I was just on the block and the street lights are being taken down. Temporary lighting will be put back in place but it is looking like that will not occur until tomorrow or even Wednesday. I have notified KPD to keep a watch until such time as lighting is restored.
Thanks for your understanding.
Wednesday, February 3, 2010
Construction Update- February 4, 2010


Construction of the 200 Block is almost finished and the sidewalks should be reopened by today. All that is left here is the 2 inch topcoat and colored bands to be poured when the temperatures allow. The roadway itself cannot be reopened back for traffic until we complete the Vine Avenue intersection construction. This work involves KUB water service as well as AT&T and will require much timing. Additionally it is an area where we have several crosswalks which will use the colored concrete so that also takes extra time.We plan to begin this work sometime in March and will likely take up to three weeks to complete.

The Contractor has used crew time wisely and has been able to keep all of his crews working consistently. The picture above is of the new curbing at the entrance to Fire Street
Additional work that will likely occur soon involves the old sidewalk along Treble Clef park ( see picture above).Wednesday, January 27, 2010
Construction Update - January 28, 2010
We finished pouring concrete for the bulb out sections at the beginning of the western sidewalk ( see pictures below) as well.



We plan to open up both sections of the sidewalk in the 200 Block on Friday and remove the fencing there so this will really open this area back up. We just finished the knee wall adjacent to the parking lot on the western side so the crosswalk along Summit Hill is all that remains before we begin work in the Vine Avenue intersection. This work will probably not take place until sometime in March as it will be involved and will require a complete closure of that intersection for around two weeks. We will have to likely flag for delivery trucks in the 200 Block and will allow valet and other parking on the 200 Block as best we can.


The first pieces of colored concrete have been poured in the 200 Block ( see next two pictures) and the remaining crosswalk at Summit Hill will be poured to the same color. I am told this is the predominant color for the rest of the project although there are some various shades for the banding yet to come.


We now have several crews working at once and the plan is to begin sidewalk construction on the eastern sidewalk of the 100 Block, beginning at Vine Avenue and working north until the supporting columns underneath begin. This work should go quickly as there is little supporting structure required. The estimate is for the construction on this piece to take one week. Then the plan is to move over onto the western sidewalk in front of FMB for another week.
Wednesday, January 20, 2010
Construction Update - January 21, 2010

Work is continuing on the sidewalks in the 100 Block of S. Gay Street. It has been challenging so far to keep access to all of the buildings while continuing the work. Southern Constructors continues to do a fine job here in trying to accommodate the needs of all of the folks affected by the construction. It is really has been a testament to their abilities in coordinating all of the subcontractors and the subcontractors of the subs as well as their own people.
As reflected in the picture below (thanks to George Richardson for this picture) the Contractor has been able to pull up the old sidewalk as one big slab which has really helped in demolition.


Again, weather permitting we hope to finish this next section in the next week or two such that we can then move over onto the eastern sidewalk in front of the Emporium around February 9 for the rest of February. This will give us time to finish up with utility relocation and the drilling of micropiles needed to create two entirely new columns to support the sidewalk in the Unarmed Merchants area. The picture below reflects just how complicated this utility relocation underground is. Although KUB has completed their work, Massey Electric is now completing the portion of the work from the retaining wall into some of the structures, primarily on Dewhirst Properties. Any outages here should be minor in length of time.
I was privileged to give KPD a tour of the underground areas as well as the areas surrounding the 100 Block last week so they can remain current with all of the access points as well as to discuss issues related to security. These folks have a tough job and I am thankful for the job they do.
I am planning another Streetscapes update meeting for February 16, 2010 at 5:00 pm at the Emporium and will get out a press release soon so please mark your calenders.
As always, thanks for your interest.
Wednesday, January 13, 2010
Construction Update - January 13, 2010
PRESS RELEASE
The right lane on the westbound side of Summit Hill Drive where it intersects with Gay Street will be closed from 9 a.m. Wednesday, January 13, through 6 a.m. Monday, January 18.
The lane closing is necessary for the completion of utility and street resurfacing work being conducted on the 200 block of Gay Street. The work is part of the ongoing Gay Street Streetscapes project.
Southern Constructors Inc. is the lead contractor for the Streetscapes project. It includes the 100 and 200 blocks of Gay Street - from Jackson Avenue to Summit Hill Drive - and involves the replacement of the street and both sidewalks in addition to other improvements.
More information about this effort is available at www.cityofknoxville.org/policy/100block/
In conjunction with 100 Block utility work, KUB will have some planned outages beginning Friday at 8:00 am until 5:00 pm to move utilities under the western sidewalk. My understanding is that folks impacted may have their power off for 2-4 hours at the longest but hopefully much shorter (see KUB Clearance request below for more detail).
Contractor’s Clearance Request Form
Email to: CustomerSupportUSAGroup@kub.org
Standard 48-hour advance notice
Clearance Date and Start Time requested
8:00AM Friday, Jan 15,2010
Contractor’s Name and phone number
Massey Electric 865-573-4200
Street Address of Clearance (or block, intersection, etc.):
111,117 S. Gay St
Purpose of the Clearance :
Relocate electric service conductors and conduit which are in way of new side walk construction.
Customer contact name and number, if applicable:
1.) 111 S.Gay St Mtr # E1H1000085
North Central Village LLC
2.) 117 ½ S.Gay St Mtr # Z1F0800727
Dewhirst Properties LLC
3.) 117 ½ (E) S.Gay St Mtr #Z1F0800729
Ayoub, Pete
4.) 117 S.Gay St Mtr #Z1F0800730
Dewhirst, David W.
5.) 117 S.Gay St Lot 1 Mtr #Z1F0800724
Dewhirst, David W.
6.) 117 S.Gay St Lot 4 Mtr #Z1F0800723
Dewhirst Properties LLC
Work Order number, if available:
CE011280
Special requests or concerns:
North Central Village LLC @ 111 S.Gay St does not appear to be occupied.
KUB Troubleman needed? Yes/No
OHC Network crew will be required to disconnect/re-connect service conductors
With temperatures warming we hope to pour concrete in several places the rest of the week beginning today.
Tomorrow the next section of sidewalk on the west side of S. Gay Street will be removed to begin that part of the construction.
Upon completion of this work, the plans now are to move over onto the eastern sidewalk in front of the Emporium around February 9, 2010 after the February First Friday.
I plan to schedule another Public meeting around the middle of February to discuss progress and future plans.
Thanks for your interest.
Wednesday, January 6, 2010
Construction Update - January 6, 2010

The next two pictures were taken under the newly constructed sidewalk. The Contractor is running heaters here to protect plumbing and other utilities.
The 200 block has been repaved and, weather permitting, we plan to close off a lane of Summit Hill next Wednesday until Monday to finish up our tie in to the 200 Block of S. Gay Street then.Wednesday, December 30, 2009
Construction Update - December 30, 2009



Sometime around the week of January 10, 2010, we will have to have a lane closure on Summit Hill for about a week to complete the roadway and sidewalk resurfacing. Of course this will be greatly dependent on the weather and I will post as soon as a date is set. Sometime soon after that bit of work we will move over into the intersection with Vine Avenue to complete that stretch. I will be discussing delivery scheduling with some of you closer to that time.


Below is the current bridge to URHbana and also to the UT Art Gallery. The next section of work is due to begin early next week. I plan to contact some of you next week to discuss scheduling. As you can see in the picture below, the door on the left which is the entrance to several apartments, will be affected and is very problematic in that it swings out and is very low. The bridging for this door will be very tricky so close coordination with everyone here will be needed.

We also plan to begin restoring the old sidewalk underground on the east side of the 100 Block next week as the KUB vault work is now completed. The next several pictures reflect the conditions underground there.

Below is another picture from the Emporium area. This side of the street is much cleaner and in better structural shape than the west side so we hope work here will progress quickly. We may be able to get to this side of the street in early 2010 depending on everyones schedule.

The columns all line up very nicely here as well (see below) as opposed to the west side where many barely fit on their caissons which created all of the column redesigns.

The picture below was taken near the old WNOX area and show the remnants of an old glass panel in the old sidewalk.

The picture below was of yet another unexpected find in the old sidewalk. Speculation is that this was a vault of the old Western Union business that existed here.

The above picture is under the Jackson Avenue ramp near the entrance to the underground on the east side. There is not an entrance way currently from lower Jackson Avenue to reach this eastern underground sidewalk area as exists on the western side with it's concrete stairway.



