Friday, November 20, 2009
The Good, the Bad, and the Ugly
We have finally poured the first bit of concrete on the western side of the 200 Block of S. Gay Street. To the left of the new sidewalk are the new streetlight boxes. The next pour will link up this section of sidewalk with the section leading to Vine Avenue. The last section of sidewalk to be poured on the west side of S. Gay Street will finish at Summitt Hill and will necessitate a lane closure in the next few weeks as we will also move over into the eastern sidewalk at that time as well.
Our construction in the 100 Block cracked a couple of windows at the UT Art Gallery when a piece of one of the beams broke loose. We apologize to the folks there and have repaired one of the windows today.
In talking to a KUB rep today on site, I have learned that KUB is planning a power outage at 120 S. Gay Street on Sunday November 22, 2009 from 9:00am until 5:00pm. Folks have been notified as usual through the KUB process but thought I might note it here as well.
Thanks for your interest.
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment