Wednesday, May 12, 2010

Construction Update - May 13, 2010

Last week proved to be a challenging one in several respects for the 100 Block of S. Gay Street construction project. The two pictures below represent some of the issues we had to deal with.
Please folks, do not park or drive on the sidewalk. I know it is tempting but the glass block panels are not designed for that and the plywood we currently have covering up the openings are certainly not strong enough to support the weight of a vehicle. Thankfully, our Contractor had a fork lift and some massive steel plates nearby to help out here. And by the way, this was just a few hours before First Friday.



We are preparing this week to pour concrete on another section of roadway from Vine Avenue northward. The plan is to pour concrete back for the roadway as both sidewalks are constructed.




The O.P. Jenkins area parking lot was repaved and striped in time for First Friday and looks really good. This has added another ten parking spaces to the area. It is my understanding that parking meters will be installed here shortly. We have also discussed striping off parking spaces in the 200 Block area even though this area was designed for a KAT bus stop and a commercial loading zone. KAT is still in the process of determining their new routes and parking is allowed after 6:00pm in commercial loading areas so we felt like it would be appropriate to go ahead and stripe off these spots for parking which will potentially add another 8 or so parking spaces to the area.


State Street from Vine Avenue to Summit Hill Drive has been removed and is being graded, with grass and some additional trees to come and we think this will be a very nice green area. Future plans for this small park are still very much in the preplanning stage and no additional funding is currently in place for any improvements. We will make sure we engage the community when we begin that process.




Below is a picture of the base that held the Treble Clef statue. My understanding is that the City Art Committee has looked over this and is in the process of requesting a RFP in the future to replace this statue.


We completed the small section of sidewalk along Summit Hill Drive by First Friday as well. Below is a picture of that construction.


We moved our efforts last week over to the western sidewalk in front of the restaurants which has been challenging. Ollantays Havana Nights has closed temporarily for renovations so that has made our efforts here a little easier as far as providing access. Still, we are working in tight quarters here. We hope to have the structural concrete all poured for this section of sidewalk by next week. Nama remains open and we thank them for their patience.



You may recognize the underground areas in the next two pictures from some very early pictures I provided of the possible 1919 storefronts.



Also next week we will begin the next section of sidewalk generally in the Unarmed Merchants area and we hope to have this section finished by First Friday in June. At that point we will begin the last section of sidewalk in front of Dewhirst Properties around the first of June and hopefully complete that by mid June.


We also plan this week and next, to begin adding the colored concrete to the eastern sidewalk so in a couple of weeks, hopefully, the eastern sidewalk will be completely finished.

On Monday, May 17, 2010, we are currently planning to restore Vine Avenue from Gay Street westbound back to its original one way designation. With the opening of the 200 Block of S. Gay Street to traffic, we no longer have the need to make this stretch two way. We will also, once again, allow for parking on Vine Avenue so we will restore the 16 parking spaces that we have previously bagged for 'No Parking". With the additional spaces created on the O.P. Jenkins area lot and the additional spaces created on the 200 Block, and with these spaces being reopened, we should finally get back to having the much needed additional parking for the area.
We can always revisit the idea of making Vine Avenue two way in the future if the need arises.
Thanks to all of those who attended the Streetscapes meeting on Monday night. We value your input into our process.
Topics discussed included the closures on Jackson Avenue in June to complete some KUB electrical work. This will force us to have a complete closure on Jackson for some period of time as there are several unknown situations we will encounter here. We have pledged, as we always do, to make this closure as brief as possible but it could last at least a week of two. This will not effect pedestrian traffic along Jackson Avenue.
Also discussed was garbage collection on the block in the future, with the discussion centering on a central collection point, possibly in the rear of the buildings, and the creation of a 100 Block Association to give us consensus on how we proceed.
The Grand Opening celebration was discussed briefly and Mickey Mallonee, Director of Special Events for the City, asked that anyone wanting to help, or having ideas, should contact her via email at MMallonee@cityofknoxville.org to discuss further. We have very tentatively discussed having this in mid September. We have placed several special events electrical boxes in the block which will enable us to easily have special events here in the future.
We will be attending demonstrations this week of the various parking kiosks we are considering for metered parking on the 100 Block. We plan to have two kiosks, each one located at the center of the block on each side of the street instead of parking meters. This new technology has never been used on public streets in the City of Knoxville. These kiosks will allow folks to pay by debit or credit cards if they desire. We will be evaluating some units that also have solar capabilities. The technology is there for folks to be able to add time to their meter via smart phone or computer as well.
We plan to use this same system when we convert the Jackson Avenue Parking lot to a paid lot in the fall. The plan is to allow the Contractor to finish his work and remove staging materials before refurbishing the lot. As I understand it, the plan is to allow for possibly the first two hours of parking to be free here. We are also planning to add a security camera which will be monitored by PBA who has the contract to manage the lot for us.
As always, thanks for your interest.

Thursday, May 6, 2010

Construction Update - May 6, 2010

Thankfully we did not receive the massive amounts of rain this weekend others experienced so we had minimal problems with our 100 Block Construction efforts.

This week has been devoted primarily to repaving the O.P. Jenkins area parking lot. We hope to have this parking lot striped for parking and reopened by First Friday tomorrow night.








We are also working on the small section of sidewalk along Summit Hill and hope to have that reopened by tomorrow as well. Unfortunately, KUB chose to block the sidewalk on the opposite side of the street at the same time which has created some pedestrian confusion. We have coordinated our efforts pretty well so far but somehow this timing did not get communicated.


The widened area of sidewalk in front of the Commerce building was also completed this week. Sometime in the next month we will probably go ahead and finish this with the colored concrete topcoat.


We moved over to the sidewalk in front of the restaurants this week. The first day we started work a little earlier than usual which generated several complaints. We apologize for the early hours but we had promised to help the restaurants as best we could and in order for them to have a lunch opening, we had to start earlier. The noise component of our work ended this morning and the next two sections will not have the same business pressures so we should work a normal schedule. Our normal contract hours are 7 to 7 .



The picture below is of the concrete saw cutting through the beams at Ollantays Havana Nights restaurant.




Our neighbors to the north have also been impacted by our construction especially Regas Restaurant. We have placed some additional signage around to help folks find their way there and we have plans to have some Streetscape work go on there in the near future.


Just another note on some of the comments on my last post. We have plans to repair existing sidewalk in the O.P. Jenkins area and to replace missing sections which were removed by utility construction.

Vine Avenue is still a subject of some discussion. As it stands currently, upon project completion, and maybe even sooner, Vine Avenue will revert back to its one way status and the parking along that section of Vine will be restored. I am getting with Engineering to understand more about this but my understanding is that for Vine Avenue to remain two way, then the parking will have to be eliminated.

Please make plans to attend our Streetscapes update meeting scheduled for Monday May 10, at 5:30pm at the Emporium.

We will be discussing the work completed to date and our future schedule and timing.

Additional topics we plan to add for discussion include garbage pickup on the 100 Block, plans for a Grand Opening Celebration, and ideas for the newly created green space along the 200 Block.
Of course First Friday is tomorrow night and I hope to see you there.
Thanks for your interest.

Thursday, April 29, 2010

Construction Update - April 29, 2010

The 200 Block of S. Gay Street is now open after being closed for nearly a year. We had hoped to open it last Monday but all of the rain created issues with the striping required before reopening the roadway to traffic. We also had folks at the City cut back some of the tree branches around the streetlights while also adding some finishing touches to the street furnishings.



The eastern sidewalk at Vine Avenue was also completed with the colored concrete this past week and the crossing ramps are under construction.

We hope to finish up the last remaining section of the eastern sidewalk in the next two weeks so all of that sidewalk will be open for First Friday on May 7. The picture below is of the massive concrete slab poured to hold the foundation wall for the new sidewalk.

Work is also continuing on the Cradle of Country Music Park site with the short section of State Street being removed and converted to grass and trees. A new sidewalk will be constructed with curb and gutter along Summit Hill Drive next week (see picture below) across the now removed section of State Street. We will have a lane closure on Summit Hill from the entrance to the O.P. Jenkins parking area to just past Cradle of Country Music Park beginning Monday morning for around a week. Much of this work will be done during two evenings.







Parking meters will be bagged for 'no parking' on the O.P. Jenkins parking lot area beginning Monday so the Contractor can begin repaving this parking area on Tuesday. We plan to have it reopened on Thursday. This parking area will be in asphalt so the work should go quickly.


Work is continuing at the intersection of Vine Avenue in anticipation of finishing the first section of roadway on the 100 Block.


The old sidewalk along Cradle of Country Music Park has been removed and a new sidewalk has been built to better align with the new sidewalk on the 200 Block.






The picture below is of the 100 Block construction taken from Vine Avenue looking north. When I looked at this picture I thought about what a chaotic scene it must be for folks on the Block everyday. The good news is we have made significant progress and I know we have folks working who really know what they are doing.
Folks on the Block could help us out by reporting anyone they see marring our newly poured concrete surfaces. We have had many instances lately of someone taking a sharp object and slicing into the new concrete. When this happens, we have no choice but to take out that section and repour new concrete which further delays the project.
Work is going well enough now that we plan to move over onto the western sidewalk in front of the restaurants by the middle of next week. Work here will probably take around three weeks to complete. As we finish this work, we will also finish that section of roadway and begin the final colored concrete sections. This next section of work will end just past the Wells Fargo office at the door leading up to apartments.
I am tentatively planning a probable final meeting to update folks on our Streetscapes project at 5:30 pm on Monday May 10, 2010 at the Emporium. I will post more on that later.

Thanks for your interest.

Wednesday, April 21, 2010

Construction Update - April 22, 2010

As many of you have noticed, we now have street lights and other street furnishings on the 200 Block of S. Gay Street. If all goes as we hope the rest of this week, we are planning to completely reopen the 200 Block and also Vine Avenue to traffic on Monday, April 26.



Once the 200 Block is reopened, we will close the short section of State Street for removal and conversion into the Treble Clef Park. The existing sidewalk will be rebuilt to tie in with our new construction. We have already removed the old sidewalk (see picture below) in anticipation of that phase of construction.


The picture below is of the completed western sidewalk on the 200 Block of S. Gay Street.

Of course work is proceeding on the 100 Block as well. Last week we completed the widened sidewalk in front of the Emporium. I was surprised at how much additional sidewalk is now available for that area.

The widened sidewalk is being created further south to catch up to the portions of sidewalk being built over the underground areas. We are planning to finish up the last section of sidewalk in about two weeks.


We are also continuing to reconstruct the roadway from Vine Avenue going north as we complete the sidewalks on both sides of the 100 Block. Right now we have the roadway completely finished almost up to Olantays Havana Nights restaurant.
Please be aware that upon the reopening of the 200 Block of Gay Street roadway, we will begin work on the parking area in front of O.P. Jenkins. Our plan now is to close off that parking area completely on May 4 for resurfacing and striping, and to have it reopened no later than May 7. This will obviously be an inconvenience for those who park there as well as the businesses but we really have no choice and we will work hard to get this completed as quickly as possible. I think everyone will be pleased with the finished look. The new surface will be asphalt so this should happen quickly.
The result of all of this work will be that by First Friday on May 7, 2010, almost all of the work for the roadway and sidewalks, including the expanded parking areas, will be completed from Summit Hill through Vine Avenue extending into the 100 Block. The construction fences will be moved back to that area as well and the eastern sidewalk will be opened.
Around mid May we will move back over onto the western sidewalk in front of the restaurants to begin finishing those last sections. Of course we still must finish these sidewalks with the colored concrete.
Last, there was a small bit of excitement in the 100 Block Sunday afternoon as someone apparently found it amusing to catch one of the Contractors Porta-Pottys on fire. Thanks to Ollantay Corujo for the brief clip below, and to Stanton Webster for letting me know so I could inform the Contractor.
I am planning to have one last Streetscapes meeting around the middle of May and will let everyone know when I have that scheduled. If anyone has any concerns or questions for that meeting, please let me know in advance and I will make sure we have folk there to address those issues.

Thanks for your interest.

Thursday, April 15, 2010

Construction Update - April 15, 2010

Work crews are making significant progress now that we have better weather. We have work proceeding in all areas of the work zone this week, including some additional sidewalk work in front of the Emporium.

With the new sidewalk poured in front of the facade, we have now moved over into the next and last section of sidewalk on the eastern sidewalk of the 100 Block of S. Gay Street.

Work crews this week have removed the old sidewalk and beams and have begun framing up for the new construction. As has often happened on this project, we have encountered some unexpected utility issues but we don't believe these will cause a delay at this time. We were also unable to take the sidewalks out as a whole as we had been able to do previously because the sidewalk and beams were apparently all poured as one some time ago. This caused the Contractor to have to jackhammer almost all of this sidewalk and manually remove it, which was a very dusty, noisy, and disruptive process.

When this section of sidewalk is complete in about two or three weeks, we now plan to begin on the western sidewalk in front of the restaurants at their request. My understanding is that they both have some remodeling planned to coincide with our construction. If all goes as we hope, we will begin this work in mid May.





The Vine Avenue intersection has worked out quite well and we hope to have the intersection in addition to the 200 Block roadway completely reopened by April 26.
The picture below is of some of the recently poured stained concrete in the intersection. We have also poured additional roadway in this area as well, while we are waiting on this section to cure.


In the week of April 26, we also plan to begin resurfacing and finishing the O.P. Jenkins parking lot which will provide some additional parking for the block upon completion. Of course the old section of State Street will be removed and incorporated into Treble Clef Park at that time as well.




Street lights and street furniture including benches and planters are being delivered and will be installed this week and next. The street lights are in the process of being installed this week and I think they are really looking good with the new sidewalk.




Around the first of June, we plan to finish up some electrical work at the intersection of Jackson Avenue which may necessitate some road closures.
I will post more about that when we have a better schedule.
As always, thanks for your interest.

Thursday, April 8, 2010

Construction Update - April 8, 2010

Work is really progressing quickly now with better weather. Vine Avenue was closed this past Monday and so far we have not had many issues with it. We are making very good progress here. The waterline in the middle of the road has now been finished (the existing waterline here basically had to be abandoned and cut off since the new waterline was installed in the 200 Block of S. Gay Street). The pictures below reflect some of that work. By yesterday afternoon the Contractor had ordered concrete for a portion of Vine Avenue.


The sidewalks on the 200 Block are now basically completed and we think they look really good. There will still be a final dressing up but folks can now get an idea of what all of the sidewalks in the Streetscapes project will look like. The plan is to begin installing street lights and street furniture next week in anticipation of the reopening of the 200 Block and Vine Avenue in a few weeks. When this block is reopened, the Contractor plans to completely repave the OP Jenkins parking lot as well and this work will include the additional parking spaces. This work should go quickly so by sometime after the first of May we are hoping to have most of the work done from Summit Hill to Vine Avenue.




We are making a lot of gains on the 100 Block at the same time and have now poured the next section of sidewalk in front of the facade between the Emporium and the Sterchi Building. The next few pictures reflect this work. The last phase of work will probably start this week with the removal of the remaining older sidewalk on the eastern side of the 100 Block. This last stretch will provide the last area of some uncertainty as the support system will consist of some grade work, some retaining wall work, and some column work. If all goes as planned here, we hope to be able to complete this section by the end of May.


Below is a picture of the rebar in place in anticipation of concrete. With this much steel in place, this sidewalk should last another 100 years!





Below is a picture of the next section of sidewalk scheduled for completion.



When we finish the work on the eastern sidewalk, we will then turn efforts back over to the western sidewalk probably starting at the section nearer Vine Avenue and working our way north. The restaurant's there are all planning some remodeling and this works with their schedules. We can also begin finishing the road behind us as we proceed.
If this works as we hope we will be finishing up at Dewhirst Properties offices in June and will begin performing finish work in anticipation of our completion date of August 15, 2010.
KUB still has some electrical work to do at the Gay Street intersection with Jackson Avenue which may require some lane closures on Jackson and we are working with them to insure that is completed well before our completion date.
Thanks to all of you for your attendance at First Friday this month and for your continued understanding. It was dusty and windy down there yesterday and we are trying to put down water to hold the dust as best we can and Southern Constructors continues to have employees washing windows.
One last note of thanks to Southern Constructors and their subcontractors, particularly Blount Excavating and Massey Electric, on behalf of many of the businesses and residents of the 100 Block. Their helpfulness and courtesy to everyone there has been noticed and is greatly appreciated.

We are also grateful to Knoxville City Council for their support in seeing this project completed on time with some certainty and also for funding the management of the Jackson Avenue parking lot.
Thanks for your interest