Thursday, June 17, 2010

Construction Update - June 17, 2010

As promised, the Contractor has now poured most of the concrete for the roadway and is beginning to pour some of the colored concrete at the intersection of Jackson Avenue at Gay Street.


Probably beginning next week we will start with the colored concrete topcoat, beginning on the eastern sidewalk where we ended a few weeks ago. Again, this work must be done at night beginning around 7:30pm. The roadway itself will be available for travel with entrances created into the effected doorways.

On July 6 we plan to shut down the Jackson Avenue intersection once again to finish up this bit of work. This intersection will receive the same colored concrete treatments as the other intersections.

As many of you have noticed, the street lights on both sides of the street are now in place and are energized. We are still working to get all of the bulbs functioning correctly however.
Below is a another picture of the 1919 construction efforts here.


I am in continued discussion with the Contractor about start times and noise so hopefully we can do better in that regard. I really believe that in another month we will be substantially finished with the major construction so please hang in there with us just a little longer.

Our friends at Slamdot wanted me to remind you of the following event tonight: Slamdot will be hosting a Farragut/West Knox Chamber of Commerce networking event on Thursday, June 17th, from 5 pm to 7 pm at the Slamdot Store downtown, located at 108 S. Gay Street, Knoxville, TN 37902. Everyone is welcome!

I am planning to set up another neighborhood meeting around the middle of July to discuss progress as well as to get ideas on plans for the Streetscapes opening Block party and ribbon cutting. I hope many of you can be there because we need your input. We are also discussing the possibility of banners being placed on the street light poles as we have done in other parts of the City.

I will be on hiatus next week but will also check on progress and if anything major occurs I will post a brief message here.

Thanks for your interest.

Wednesday, June 9, 2010

Construction Update - June 10, 2010

As complicated and challenging as this Streetscapes Project has been, the original construction must have been equally as daunting as evidenced by the following picture pre 1919.


Of course below is a picture of the completed look after 1919 completion.


We have now reopened Jackson Avenue upon completion of utility work. Unfortunately we must close Jackson Avenue one more time for approximately two weeks, probably beginning on the Monday after First Friday in July, to finish repaving this area.


We have also finished the last section of sidewalk on the western side of S. Gay Street (see next two pictures).

Street lights have been installed on both sides of the street and the lights are energized on the eastern section.We hope to have all of the street lights turned on by the end of next week.

The road work is now coming along at a rapid pace and by the end of next week we are hoping to have all of the concrete poured for the roadway.


Sometime around the week of June 21 we will begin finishing the sidewalk sections with the colored concrete. This work will be done primarily at night beginning around 7:30pm as the concrete is temperature sensitive. This pour of concrete should be set up by the next morning. After we get a few sections poured we will have a real good idea of timing for the remaining sections. While this work is being done, the street itself will be used for pedestrian traffic. We are aware of the noise issues and are not planning to use any equipment except for the concrete trucks and the crews themselves with wheelbarrows. Access will be provided for all of the entrances as we go.


We are getting to a point in construction where we can all see the finish line. Hallelujah!

Thanks for your interest.

Tuesday, June 8, 2010

Jackson Avenue

We hope to reopen Jackson Avenue by tomorrow morning, June 9, 2010

Wednesday, June 2, 2010

Construction Update - June 3, 2010

As many of you know, we have now closed the intersection of Jackson Avenue and Gay Street for about two weeks for some much needed electrical work for KUB.

I thought I would post these two old pictures I had of that intersection. The first picture is of the first reconstruction efforts in 1919 and the second is of a parade downtown after construction.


Of course every one hundred years or so some maintenance is required so here we are again.

The picture below is of some additional trolley rails we encountered.

When the Gay Street Viaduct was reconstructed the grades were such that some of the brickwork for the Jackson Avenue ramps had to be covered with pavement to match grade. The picture below is of some of that brickwork we have uncovered for this phase of work.
Some folks had called with questions about our traffic control signs and those should have been better positioned by now. Please let me know if any problems are noted.

Of course, one of the main issues here is dealing with an old KUB vault in the middle of the intersection.


The 100 Block of S. Gay Street is really starting to take shape now as reflected in the next picture. The structural concrete has been poured back for the sidewalk in front of the restaurants and also for the next section near Unarmed Merchants. The last remaining section is being removed today near Dewhirst Properties and we hope to have that last section back in concrete in about two weeks. In the meantime we will also pour concrete for the remaining roadway sections and also begin the colored concrete topcoat. This bit of work for the topcoat will occur primarily at night after 7:30 and will only involve concrete trucks and wheelbarrows so we hope to make as little noise here as possible. The concrete should set up by the next morning so most folks will not be as inconvenienced.

We have placed a sign at the O. P. Jenkins area parking area intersection with the 200 Block for safety and will continue to monitor its effectiveness.


Lest we forget, we have come a long way on improvements for this area. Thanks to Michael Haynes for providing the following picture of the 100 Block from the early 70's I am guessing.


This weekend will bring many great events downtown with First Friday on June 4 along with our first ever Biscuit Festival so please come downtown and enjoy all of the festivities and make sure to visit all of our merchants while you are here, particularly our friends on the 100 Block of S. Gay Street such as Eleven, URbhana, Unarmed Merchants, Slamdot, and Nama. Ollantay's Havana Nights is undergoing some renovation as I understand it, and will be reopening soon.
Also don't forget Regas Restaurant just on the other side of the Gay Street Viaduct.
Be sure to visit Hola's office at the Emporium while you are there on Friday. Works by Colombian artist Jorge Yances will be on display, along with works by many other artists in other sections of the Emporium and the UT Art Gallery next door.
Of course many other fine artists will have their work displayed at all of the galleries downtown as well and I know they all would appreciate your continued support.
City People will be sponsoring a downtown dash tomorrow as well. Registration 6-7pm outside of Pete's on Union Ave. Race begins at 7:30pm!

Lastly, Slamdot will be hosting a Farragut/West Knox Chamber of Commerce networking event on Thursday, June 17th, from 5 pm to 7 pm at the Slamdot Store downtown, located at 108 S. Gay Street. For more details on this event, please visit the Slamdot website at the link on this page.
Thanks for your interest.

Wednesday, May 26, 2010

Construction Update - May 27, 2010

Please don't forget the Jackson Avenue closure scheduled for June 1, 2010 at the Gay Street Viaduct. This closure will completely block off Jackson Avenue there for around two weeks for KUB electrical work. After that time we will reopen the road for a short time before we finish repaving as part of the Streetscapes project.

The sidewalk along Jackson Avenue will not be affected by this temporary closure.

We have really poured a lot of concrete the last few weeks and this week was no exception.The pictures below are of the roadway areas recently restored as well as the sidewalk areas in front of the restaurants.





The Contractor has now moved over into the next to the last section of the western sidewalk. The pictures below were taken in front of the former Harolds deli site and also Unarmed Merchants. We are working on the columns and beams in this area and hope to have the structural concrete poured back here by First Friday on June 4.




Work is continuing on finishing up the entire eastern sidewalk with the colored concrete topcoat. The Contractor has started the process of framing this area beginning at Vine Avenue and will probably begin pouring concrete here next week.


We have ordered traffic control signs to go at the O. P. Jenkins parking lot area where the parking area intersects the 200 Block of S. Gay Street sidewalk and we hope to have those installed this week.

As most of you know, the 100 Block is a very congested work site these days so please help us all out by using caution. We have tried to create several walking paths around the area but with so many paths having been created, there may occasionally be conflicts with vehicles entering the site. We apologize for all of the occasional inconvenience when folks find the pathway they used yesterday now blocked, but to finish the project we need this flexibility.
By First Friday, we hope to have almost half of the 100 Block poured back with structural concrete so please hang in there with us just a little longer.
The look of the 100 Block will change dramatically in the next few weeks and I hope everyone will be pleased with the outcome.
Thanks for your interest.

Friday, May 21, 2010

Construction Update - May 21, 2010

The Contractor wanted me to let everyone know he will not be working Saturday, May 22 but will work on Sunday May 23.

He is working on the supporting structures under the western sidewalk and he is at a stage where he applies an epoxy which only has a 24 hr timing so he can proceed with this work on Monday.

Thursday, May 20, 2010

Construction Update - May 20, 2010

We continue to make significant progress on the 100 Block of S. Gay Street despite the periods of rain we have experienced lately. I did not realize how ominous the sky looked when I took the following two pictures.


The western sidewalk work is progressing and we are also pouring concrete for the roadway as we go, progressing from Vine Avenue northward.
Plans are to begin the colored topping for the eastern sidewalk this week. This work will occur primarily after hours so issues of building access can be minimized.
We believe once we get started here, work will proceed quickly.
We are all hoping to have the entire eastern sidewalk section completely finished by First Friday in June.
The picture below is of the rubber coating which is used to set the new colored concrete. Use of this product, along with extensive caulking, will minimize any water issues in the future.
The amount of caulking needed on this job is measured in miles and the 200 Block is currently being caulked between each band and section of sidewalk.

The work on the western sidewalk of the 100 Block is proceeding as we had hoped.
We now have the structural concrete poured for the sidewalk in front of the restaurants and have proceeded into the next section of sidewalk which is in front of Wells Fargo and Unarmed Merchants. Our plans are to have the structural concrete poured back here by First Friday in June as well.



The picture below is of the new sidewalk in front of Nama and Ollantays Havana Nights and also of the new concrete poured for the eastern portion of the roadway. The remaining western section of roadway here will be poured today, as I understand it.


I attended a demonstration for a parking kiosk this week. Our plans are to have two parking kiosks located on each side of the street in the center of the block. The City of Knoxville has not used this technology before for on street parking. The kiosk shown in the picture below is named "Luke" after the scene in Cool Hand Luke where Paul Newman, how should I say this, 'confiscates' the contents of parking meters. This machine is actually pretty amazing in its capabilities. I will post more on this later as we decide which options are used.
This type of meter will also be used on the Jackson Avenue parking lot when it becomes a managed lot this fall.


Thanks to Richard Huskey of Southern Constructors for these nice aerial shots taken of our work site.




There have been several close encounters of pedestrians and cars exiting the O.P. Jenkins parking lot in the 200 Block now that that section of roadway has reopened and City Engineering will be placing some traffic control measures here to better alert drivers and pedestrians to the hazards.
In the meantime, please be very careful here along the eastern sidewalk.
Vine Avenue has now reverted back to its original one way designation without any issues as far as I know.
Lastly, in order to finish up the remaining electrical work, we plan to completely close Jackson Avenue at the Gay Street Viaduct beginning June 1, 2010 for approximately two weeks. We will need one last closure here, probably in July, to finish up. Pedestrian traffic will be maintained at all times.

Thanks for your interest.