Friday, July 23, 2010
O. P. Jenkins Parking Lot area
Wednesday, July 21, 2010
Construction Update - July 22, 2010

There are still many items to finish on our punch list and we will continue to work on those issues after the road is opened. Certainly caulking all of the areas will take some time.
The sod for the Cradle of Country Music Park should also arrive finally next month so we can begin to finish that bit of work.
We are beginning to have issues with folks parking on the 100 Block, particularly at night. We have instructed KPD to keep a close watch on this and if you park there you will be cited and/or towed. We have placed no parking signs there, but folk are removing the barricades and entering the work zone. We all want this project to finish and have the road reopened as soon as possible and this is the type of situation that could cause real delays.
Last, congratulations to our friend Stanton Webster of Nama on the birth of his daughter, Sophia Estelle Webster.
Thanks for your interest
Thursday, July 15, 2010
Construction Update - July 15, 2010
We all want it to be right when we are finished here so spending a little extra time now seems to make a lot of sense.
Thanks to all of you for attending the 100 Block meeting this week. We discussed parking issues including signage on the Gay Street Viaduct and City Engineering is investigating those issues for me. Commercial loading zones and possible 15 minute parking spaces also had discussion. This is an issue that exists all over downtown and we are in the process of determining a solution that works for everyone.
A Committee is forming to plan the Block party planned for late August or September and this will be coordinated through our Office of Special Events. Contact them if you wish to be included.
Lastly, we were glad to hear that plans are being made to reconstitute the 100 Block Neighbourhood Association. I am sure you will be hearing more about that in the near future. Sean Christman of Slamdot will be heading up this organization.
As most of you know, we have only a little sidewalk work in front of the former VMC building left to finalize and we will finish this up this week. Other than caulking, this will finish up all of the sidewalk work for the project.
We are hoping to have our planter boxes completed but we continue to have delays with our vendors due to Nashville flooding. We plan to install the trees in September and these will be 20' to 30' Elms so the effect should be quite dramatic.
Overall though, I think the block is looking great. The 200 Block has been completed for some time, the street lights are in and are functioning, the street furniture is in place, O.P. Jenkins Parking Lot area has been completely refurbished, Fire Street Alley has been completely rebuilt, and the Cradle of Country Music Park has been expanded. All of the new utilities are in place and are on line, and the underground areas have new pavement.
The picture above was sent to me by a friend and was taken from a book he received recently.The book, "Knoxville - A Pictorial History", has this photograph and the accompanying text:
"In 1869, S.T. Post and Son started making wagons and carriages. In 1978, Post and Company is still in business, but they make truck bodies nowadays. This photo, taken from Summitt Hill in 1872, shows Post's original location. Gay Street goes from left to right in the foreground. Peabody School is the large cupolaed building just below the left horizon. East Tennessee, Virginia and Georgia railroad trains - now the site of the Southern railroad yards - are below the Peabody. The circus was held just above the pond near the center of the picture. Central Avenue (originally Crozier Street) can just be seen halfway up on the right behind the white house."
Thanks again to all of the folks on the bock for their patience and understanding throughout this complicated project.
As always, thanks for your interest.
Wednesday, July 7, 2010
Construction Update - July 8, 2010
The picture below is of the intersection of Jackson and Gay Street probably in the late 1890's. It is interesting to note that this was before the Emporium was built. The lower right corner of the photo shows the depression in which the Emporium Building was finally constructed. Note the wooden fence along Jackson to keep folks from falling in the steep depression.Topics of discussion will include the Block Party, 100 Block Association, and any construction issues.
Wednesday, June 30, 2010
Construction Update - July 1, 2010
We will most certainly still have occasional lane closures for at least another month along the block but we are hopeful that at least one lane can remain open from here on out.
We will not plant the trees until the fall, probably in November and given their size, we will have to have some lane closures then as well.
The sod we had ordered for the Cradle of Country Music Park was to come from Nashville but because of the flooding there, this has been delayed so we still will have that bit of work to do.
Of course First Friday is July 2 and we hope to have much of the colored concrete poured on the eastern sidewalk by then. We must wait, however, until we begin our work on the final section of sidewalk in front of the Emporium so we can make sure the colors all are uniform with the concrete on Jackson Avenue.
The Jackson intersection will receive the same colored concrete treatments as the intersection of Vine Avenue and Gay Street. This will necessitate one remaining two week closure of this intersection beginning July 5, 2010 at 7:00 am.
http://knoxvillefirstfriday.com/wp/
http://www.knoxalliance.com/
http://knoxvillemarketsquare.com/
Below are pictures of the Emporium building shortly after the road was reopened in 1919 and the next picture is of some of the business that went on there.


Since we have been able to move more quickly on this final bit of work, we will not have the parking kiosks in place by the ribbon cutting so we will simply stripe off the parking stalls and allow free parking until we can get these units installed.
Also, we apologize for all of the confusion over the misaligned parking meters on the O. P. Jenkins parking lot. Hopefully in a couple of weeks we can get that situation rectified but I am happy that KPD will not be enforcing parking meter violations here until we are able to restripe that lot. This work is now tentatively scheduled for July 11th. If all goes according to plan, we will post signs about this on Friday July 9, 2010 and clean the lot on the evening of July 10, 2010.
I am planning another 100 Block neighborhood meeting to be held at 5:30pm on Tuesday July 13 at the Emporium. I really hope many of you can attend to help us plan for the opening celebration and also to begin discussion about an 100 Block Neighborhood organization. Of course we will also review our progress on the project and the next steps until completion.
I hope everyone has a safe and enjoyable 4th of July Holiday. I know many excellent events are planned downtown .
Thanks for your interest
Thursday, June 17, 2010
Construction Update - June 17, 2010

Probably beginning next week we will start with the colored concrete topcoat, beginning on the eastern sidewalk where we ended a few weeks ago. Again, this work must be done at night beginning around 7:30pm. The roadway itself will be available for travel with entrances created into the effected doorways.
I am in continued discussion with the Contractor about start times and noise so hopefully we can do better in that regard. I really believe that in another month we will be substantially finished with the major construction so please hang in there with us just a little longer.
I am planning to set up another neighborhood meeting around the middle of July to discuss progress as well as to get ideas on plans for the Streetscapes opening Block party and ribbon cutting. I hope many of you can be there because we need your input. We are also discussing the possibility of banners being placed on the street light poles as we have done in other parts of the City.
Wednesday, June 9, 2010
Construction Update - June 10, 2010
Of course below is a picture of the completed look after 1919 completion.
We have now reopened Jackson Avenue upon completion of utility work. Unfortunately we must close Jackson Avenue one more time for approximately two weeks, probably beginning on the Monday after First Friday in July, to finish repaving this area.
We have also finished the last section of sidewalk on the western side of S. Gay Street (see next two pictures).
Street lights have been installed on both sides of the street and the lights are energized on the eastern section.We hope to have all of the street lights turned on by the end of next week.
The road work is now coming along at a rapid pace and by the end of next week we are hoping to have all of the concrete poured for the roadway.
Sometime around the week of June 21 we will begin finishing the sidewalk sections with the colored concrete. This work will be done primarily at night beginning around 7:30pm as the concrete is temperature sensitive. This pour of concrete should be set up by the next morning. After we get a few sections poured we will have a real good idea of timing for the remaining sections. While this work is being done, the street itself will be used for pedestrian traffic. We are aware of the noise issues and are not planning to use any equipment except for the concrete trucks and the crews themselves with wheelbarrows. Access will be provided for all of the entrances as we go.
We are getting to a point in construction where we can all see the finish line. Hallelujah!
Thanks for your interest.