We are very much encouraged by the progress we are making on the 100 and 200 Block of S. Gay Street. As I noted last week most of the utility work is now done and we are now in the roadway and sidewalk construction phase. So far the weather has cooperated enough to allow us to pour a good amount of concrete.
The picture below is the first pour of concrete in front of the VMC building on the west side of S. Gay Street.
We have also started the next section of sidewalk ( see below). We have quickly learned that we will probably be building and rebuilding bridge sections as work progresses depending on the work to be done and the situation with the building occupants.
The 200 Block is really coming along such that we hope to have all of the concrete in place by the end of the year with a possible reopening of the 200 Block to 2 way traffic by the end of January. We will have some work to do at the first of the year which will necessitate a lane closure on Summit Hill for maybe two days to finish up here. The pictures below show the 2oo block formed up and then with concrete poured. All of the sidewalks have now been reformed on both sides of the street and only the roadway is remaining to be surfaced.
The 200 Block is really coming along such that we hope to have all of the concrete in place by the end of the year with a possible reopening of the 200 Block to 2 way traffic by the end of January.
ReplyDeleteused bucket trucks
Will the crews be working on New Years Day?
ReplyDeleteNo, the crews are off for New Years and plan to knock off early New Years Eve as well.