Wednesday, December 30, 2009

Construction Update - December 30, 2009

As we had hoped, we have now been able to complete most of the 200 Block of S. Gay Street roadway and all of both sidewalks have now been reformed with concrete. The 2 inch pour of concrete is yet to come which will have the coloring and banding. The three pictures below reflect the current status of work here.







Sometime around the week of January 10, 2010, we will have to have a lane closure on Summit Hill for about a week to complete the roadway and sidewalk resurfacing. Of course this will be greatly dependent on the weather and I will post as soon as a date is set. Sometime soon after that bit of work we will move over into the intersection with Vine Avenue to complete that stretch. I will be discussing delivery scheduling with some of you closer to that time.

The first section of sidewalk has been poured in the west side of the 100 Block and we plan to pour the concrete needed for the next section in front of UHRbana tomorrow.




Below is the current bridge to URHbana and also to the UT Art Gallery. The next section of work is due to begin early next week. I plan to contact some of you next week to discuss scheduling. As you can see in the picture below, the door on the left which is the entrance to several apartments, will be affected and is very problematic in that it swings out and is very low. The bridging for this door will be very tricky so close coordination with everyone here will be needed.

Other work being completed includes water service on the western side of the 100 Block. This switchover could cause very temporary water cutoff for some while the switch is made from old service to new service. I am told the outage would take no more than 20 minutes at a time and none of the restaurants would be affected.


We also plan to begin restoring the old sidewalk underground on the east side of the 100 Block next week as the KUB vault work is now completed. The next several pictures reflect the conditions underground there.


The picture above is of the old sidewalk beside the Emporium. Note the glass block panels above.

The picture below is of the older sidewalk looking toward the Sterchi Building.


Below is another picture from the Emporium area. This side of the street is much cleaner and in better structural shape than the west side so we hope work here will progress quickly. We may be able to get to this side of the street in early 2010 depending on everyones schedule.


The columns all line up very nicely here as well (see below) as opposed to the west side where many barely fit on their caissons which created all of the column redesigns.


The picture below was taken near the old WNOX area and show the remnants of an old glass panel in the old sidewalk.


The picture below was of yet another unexpected find in the old sidewalk. Speculation is that this was a vault of the old Western Union business that existed here.



The above picture is under the Jackson Avenue ramp near the entrance to the underground on the east side. There is not an entrance way currently from lower Jackson Avenue to reach this eastern underground sidewalk area as exists on the western side with it's concrete stairway.

I hope everyone has a very Happy New Year and for all of you planning an evening for First Night downtown, don't forget to patronize the shops on the 100 Block as well.

Thanks for your interest.