Wednesday, June 9, 2010

Construction Update - June 10, 2010

As complicated and challenging as this Streetscapes Project has been, the original construction must have been equally as daunting as evidenced by the following picture pre 1919.


Of course below is a picture of the completed look after 1919 completion.


We have now reopened Jackson Avenue upon completion of utility work. Unfortunately we must close Jackson Avenue one more time for approximately two weeks, probably beginning on the Monday after First Friday in July, to finish repaving this area.


We have also finished the last section of sidewalk on the western side of S. Gay Street (see next two pictures).

Street lights have been installed on both sides of the street and the lights are energized on the eastern section.We hope to have all of the street lights turned on by the end of next week.

The road work is now coming along at a rapid pace and by the end of next week we are hoping to have all of the concrete poured for the roadway.


Sometime around the week of June 21 we will begin finishing the sidewalk sections with the colored concrete. This work will be done primarily at night beginning around 7:30pm as the concrete is temperature sensitive. This pour of concrete should be set up by the next morning. After we get a few sections poured we will have a real good idea of timing for the remaining sections. While this work is being done, the street itself will be used for pedestrian traffic. We are aware of the noise issues and are not planning to use any equipment except for the concrete trucks and the crews themselves with wheelbarrows. Access will be provided for all of the entrances as we go.


We are getting to a point in construction where we can all see the finish line. Hallelujah!

Thanks for your interest.

No comments:

Post a Comment