Friday, May 15, 2009

Construction Update

The test drilling through the sidewalk began this morning. A pedestrian pathway has been created around the drill rig for sidewalk access. This first bore hole is around the middle of the block. Yesterday we reported that the plan was to begin closer to Volunteer Ministry but the decision was made this morning to start at this location instead.

Work on a waterline is still scheduled to occur on Monday at 3pm. I have been assured that one lane of Vine will remain open which should accommodate both folks using the parking lot and the valet parking needed for the restaurants.

A protective fence has also been erected as excavation continues.